    Samsung Electronics' Investors Forum - June 4 2018

    Samsung Electronics held an Investors Forum June 4 2018 in Singapore. The transcript is available here: http://irsvc.teletogether.com/sec/20...8if_script.pdf

    Regarding semiconductor process updates, it is quite brief, here is what was mentioned in that script:

    1. Risk produce 11LPP and 8LPU now.
    2. 7LPP risk produce second half of this year. Next year 5LPE and 4LPE risk production.
    3. EUV NXE:3400 currently approaching 1000 wafers per day. Target 1500 wafers per day by 2020. (This is really slow by the way. 6000 wafers per day is a reasonable expectation for leading edge NXT tools.)
    4. 3 nm move to MBC-FET (stacked surrounded gates). 0.75V is FinFET limit of supply voltage.
    5. 28LPP move to 28FDS and 18FDS (FDSOI). 28FDS now and 18FDS next year. NXP first adopter, but also popular in Japan.

    3 Not allowed!
    Last edited by Fred Chen; 07-09-2018 at 03:22 PM.
     

  2. #2
    Member
    Join Date
    Sep 2014
    Posts
    42
    Thumbs Up
    Received: 50
    Given: 18
    Interesting!

    2. 7LPP @ H2 2018 --> That means EUV volume production in H1 '19, or am I being too optimistic?
    3. That' s 40/hr right, I thought the aim with 250W source was 125/hr? Still quite far apart. Is availability (downtime, planned maintenance) maybe still a problem?
    5. Nice, they' ll provide 18FDS 'next year'. NXP => Would be the i.MX 6 I'd guess?

    0 Not allowed!
     

  3. #3
    Expert
    Join Date
    Mar 2012
    Posts
    561
    Thumbs Up
    Received: 191
    Given: 163
    Quote Originally Posted by hkwint View Post
    3. That' s 40/hr right, I thought the aim with 250W source was 125/hr? Still quite far apart. Is availability (downtime, planned maintenance) maybe still a problem?
    It looks like they are increasing the doses even further, to reduce the CD nonuniformity as well as to avoid stochastic missing or bridging features. They also mentioned high-sensitivity resist. Downtime still needs to be considered as well.

    0 Not allowed!
     

  4. #4
    Member
    Join Date
    Oct 2014
    Posts
    40
    Thumbs Up
    Received: 13
    Given: 1
    How many machines do they have running; now and say in a year? 10-12 at most? at 40wph that seems like a hobby with say 9600 wafers a day.

    0 Not allowed!
     

  5. #5
    Expert
    Join Date
    Mar 2012
    Posts
    561
    Thumbs Up
    Received: 191
    Given: 163
    Quote Originally Posted by Chipper View Post
    How many machines do they have running; now and say in a year? 10-12 at most? at 40wph that seems like a hobby with say 9600 wafers a day.
    I suppose it makes most sense to have each tool do one BEOL layer (their VLSIT paper indicated they covered entire BEOL), so that would be ~ 30000 wafers per month, as long as all of the tools are up.